Road construction coming to an end

Phase I of the Petersburg Road Improvement Project is coming to an end – and Dowl HKM Project Engineer Matt McGuan recapped the construction activities over the last two weeks during a recent meeting.

“All curb and gutter have been poured except for two damaged pieces by Tides Inn,” he stated. “We have also poured sidewalks on Dolphin Street from the top of the hill down to the PIA parking lot and sown to the Nordic Drive intersection.”

Concrete and parking aprons have been poured on Dolphin and the majority of the sidewalks along both sides of Nordic Drive have been completed and Dolphin Stre...

 