SECON Construction completed drainage construction and back-filled the west side of Excel Street between the harbor office and Main Street this past week. Work continues heading north on North Nordic Drive where they will install storm and sanitary drains on the Coastal Cold Storage side of the street. State Project Inspector Jim Stolpe said the company is about a week behind schedule due to the recent freezing weather. He said SEACON’s concrete plant arrived in town and is being set-up. He encouraged the public to be patient as the work progresses this spring and summer and he asked that driv...