Matt McGuan, Project Engineer for DOWL HKM, reported that the concrete pavement has been poured on the east side of Nordic Drive in front of the Trading Union Hardware Store during a road construction progress meeting Tuesday afternoon.
“SECON has completed the installation of the storm drain pipe and structures on the Phase 2 portion of Nordic Drive,” McGuan stated. “They have also completed the demolition of Excel Street with the exception of the south sidewalk.”
McGuan also said that the installation of the storm drain pipes and structures on Excel Street are about 90 percent complete.