The Petersburg Road Improvement Project continues to progress through Phase 2 as DOWL HKM Project Engineer Matt McGuan, along with SECON Project Superintendent Bryce Iverson explained what has been done with the project and what is to come for the next two weeks with emphasis on scheduling around Mayfest and vandalism to poured concrete.
“At this time both lanes of Nordic Drive from the north end of the project to the Dolphin Street intersection have been poured,” McGuan stated. “The northbound lane is open for traffic and the southbound lane will be used for parking only. The only traffic thr...