Nordic Drive paving to begin between Gjoa and Fram

The Petersburg Road Improvement Project is moving better than scheduled due to weather and ability to continue moving from one Phase of the project to another quickly.

“We have been given the ability to continue on with the demolition of one section while finishing the previous one,” SECON Project Superintendent Bryce Iverson said. “This is making the transition much easier and faster.”

Dowl HKM Project Engineer Matt McGuan and Iverson updated the public in a progress meeting Wednesday afternoon.

McGuan reported that over the last two weeks the storm drain pipes and structures on the east side...

 

Reader Comments(0)