The first pieces of the floats have arrived for the Drive Down Dock project, though complete installation is still to come as the modular sections are linked, only slightly impeded by the sudden surplus of snow.
Currently, three pieces have arrived, Harbormaster Glo Wollen reported on Monday. “Tamico (Construction) splashed at (Alaska Marine Lines) last night and towed them over to the Martinsen Dock where they are working (on Monday) to bolt them together.”
Another 10 sections are to come, with semi-regular deliveries “every couple of weeks” of perhaps three sections expected throughout the w...