December 4, 1915 – The work of digging holes for the electric light poles was started Wednesday morning, the digging tools having finally reached here on Tuesday's steamer. Forty-seven poles are to be put up now, to be added to from time to time as extension of the line is called for. The power house is completed and ready for the machinery, with the exception of laying the concrete foundations. When the poles are in place, the work of stringing wires and wiring buildings will start, as practically all material for this work is now here.