Medical Center kitchen remodel nears completion

The remodel of the Petersburg Medical Center kitchen facility is nearing completion. Food service will resume in the new kitchen on Jan. 8.

The hospital board approved the budget of up to $292,000 in March and made plans to use the Ocean Beauty bunkhouse kitchen to prepare meals during the remodel.

Project supervisor Marty Sussort with Alaska Commercial Contractors in Juneau said the project entailed breaking up the kitchen floor to access waste lines that had plugged or failed. "We found the soil under the floor had subsided significantly and structural concrete footings had to be poured befo...

 

Reader Comments(0)

 
 
Rendered 07/22/2024 08:25